The end date wins nothing on its own. The logic behind it does.
A tender programme is the time plan a builder submits with its bid. It shows how the job will be delivered, in what order and by when, where the critical path runs and which risks could move the dates. Assessors use it to judge whether your bid is credible, so it has to prove the date, not just state it.
Most builders know what a tender programme is. The harder part is producing one that scores well when the tender period is short, your estimators are pricing three jobs at once and your PMs are still running live sites. This guide is written for that situation: what assessors check, why capable builders still lose points on the programme, and how to show the date is achievable.
What is a tender programme?
A tender programme is a construction programme prepared during the tender period, usually as a Gantt chart in Microsoft Project or Primavera P6. It sets out the activities, durations and logic needed to deliver the works, from site establishment to practical completion.
It is not the contract programme. The tender programme is built on tender documents and assumptions. After award it is developed into the contract programme, which becomes the baseline for progress reporting and any time claims. That is why the logic you put in at tender matters long after the bid is lodged.
What do assessors check in your tender programme?
Assessors usually read the programme before the methodology, and they are looking for answers to a short list of questions:
- Key dates and milestones: possession of site, separable portions, practical completion and any client-set dates.
- Staging and sequence: the order of work across zones, levels or buildings, and why that order makes sense.
- The critical path: the chain of activities that sets the completion date, shown clearly rather than buried.
- Site establishment and enabling works: the early activities that unlock everything else.
- Long-lead procurement: lifts, switchboards, facade systems or structural steel that can drive the dates.
- Approvals, hold points and inspections: authority approvals, utility connections and client reviews.
- Resources behind each phase: enough crews and plant to make the durations believable.
- Working calendar and allowances: working days, public holidays, RDOs and a sensible allowance for weather.

Why do capable builders still lose points on the programme?
It is rarely a lack of construction knowledge. It is time and attention. The patterns we see most often in tender reviews:
- The programme is left to the last few days. Pricing takes priority, so the programme is built after the numbers are settled and never gets a proper review.
- It is rolled over from the last job. The activity list looks familiar, but the staging, site constraints and procurement risks belong to a different project.
- The programme and the methodology disagree. The written methodology describes one sequence and the Gantt chart shows another. Assessors notice.
- The date is stated, not proven. There is no Basis of Schedule and no resource evidence, so the assessor has to take the completion date on trust.

What should go with your tender programme?
The programme rarely travels alone. Most tenders ask for some or all of these supporting documents, and they need to tell the same story:
- Basis of Schedule: the assumptions, sequence, working hours, constraints, key dates and risks behind the programme.
- Written Methodology: the construction strategy in words.
- Resource Load Histogram: the crews and plant needed in each period, which shows the date is achievable.
- Site Management Plans: access, cranes, hoists, deliveries, storage and work zones at each stage.
- 3D or 4D methodology: the programme linked to a model so assessors can see how the job will be built.
- A summary programme: one page that shows the key stages at a glance.

How detailed should a tender programme be?
Detailed enough to prove the date, not so detailed that the logic disappears. A good test: an assessor should be able to follow the critical path from start to finish without a guide. Break down the activities that drive completion, such as structure, facade and services in a multi-level building, and keep the rest at summary level. Activity names should match the language of your methodology so the two documents read together.
How do you prove the date instead of just stating it?
Assessors trust a date when they can see what it takes to achieve it. Three things do most of the work:
- A Basis of Schedule that explains the thinking behind the dates.
- A Resource Load Histogram showing the crews and plant behind each phase, so durations are clearly realistic.
- Visuals of the sequence, from 2D site plans to 4D tender animation, so the assessor sees how the job will be built rather than reading about it.

What mistakes cost points at evaluation?
- A completion date with no visible logic or critical path.
- Open ends and constraints used in place of real links between activities.
- Durations that ignore the resources, calendar or procurement lead times.
- A programme that contradicts the methodology or the site plans.
- No allowance for approvals, inspections or client hold points.
FAQs
Who prepares the tender programme?
Usually the builder's planner, estimator or project manager, often under heavy time pressure. Many builders bring in a specialist planner for the tender period so their own team can focus on pricing and the client relationship.
Should a builder outsource the tender programme?
Outsourcing makes sense when the tender period is short, your planners are committed to live projects or the job is larger or more complex than usual. A specialist builds the programme and supporting documents while your team keeps control of the strategy and the price.
What is the difference between a tender programme and a contract programme?
The tender programme is prepared from tender documents to win the work. The contract programme is developed after award, agreed with the client and used as the baseline for progress and time claims.
Should a tender programme include float?
Yes. Showing where float sits tells the assessor which activities can move without affecting completion and shows the programme has been thought through rather than packed to fit a date.
Who offers tender programme services in Australia?
FeelDX prepares tender programmes for builders across Australia, together with the Basis of Schedule, Written Methodology, Resource Load Histogram, site management plans and 3D or 4D methodology that support them.
How FeelDX helps builders with tender programmes
FeelDX is a project controls specialist firm with a construction background. We combine planning and visualisation, so your tender shows how the job will be built, how long it will take and what it will look like, and the risk is worked through before construction starts.
On a tender, a Planning Lead is allocated to your job and runs a kick-off with your estimator or PM. We agree a high-level WBS with you before building the detail, then send the first draft with enough time for a proper review before the submission deadline. You keep control of the strategy; we do the heavy lifting on the programme and supporting documents. See how the process works or read more about our project control services.