Delay Notices: Programme Evidence to Send on Time

A delay notice is the builder's formal written notice, under the contract, that an event has delayed or is likely to delay the work. It should name the cause, when it started, the activities affected and the likely effect on completion. Programme evidence attached early protects your later extension of time claim.

You know the week. Design information for the level 3 transfer slab is late, the formwork crew is standing around and the PM is juggling subcontractors, a pour and a client walk. Everyone means to send the notice once the full picture is clear. Ten days later an email goes out saying the builder "reserves its rights". By then the notice window in the contract has closed, and the superintendent says so.

The delay was real. What was missing was a notice on time, backed by enough of the programme to show why it matters.

What does a delay notice need to say?

Contracts word it differently, so start with the clause in yours. Most standard forms used in Australia expect a notice to cover the same core points, and a notice that misses one of them is easy to reject.

  • The cause. What happened, described as a fact: the late instruction, the variation, the latent condition or the defined weather event.
  • When it started. The date the delay began, or the date you became aware of it.
  • The work affected. The activities and areas held up, named the way they appear in the programme.
  • The likely effect on completion. Your current view of whether the date for practical completion will move, even if the extent is not yet known.
  • The contract reference. The clause you are notifying under, sent to the person and address the contract specifies.
Diagram of the five parts of a delay notice: cause, start date, work affected, likely effect on completion and contract reference
A notice that covers all five points is hard to dismiss, even when the full extent of the delay is still unknown.

This is general information, not legal advice. Your contract sets the actual notice periods, time bars and form of notice, so read the clause at the start of the job and get legal input where the stakes are high.

 

What programme evidence should go with the notice?

A notice does not need a full delay analysis. It needs enough programme evidence to show the superintendent that the claim, when it comes, will rest on the programme and not on opinion.

  • The current programme update. Progress statused to a date just before the event, so it shows where the job actually was.
  • A marked-up excerpt. The affected activities highlighted, with the logic that links them to the critical path and completion.
  • A preliminary impact. A first estimate of the effect on completion, clearly labelled as preliminary and to be updated.
  • The float position. Whether the affected path had float, and how much, so nobody assumes the delay is absorbed.
  • References to the records. The RFI, instruction, diary entries and dated photos that confirm the cause and the start date.
Workers in hard hats and safety harnesses climbing tall reinforcement cages for concrete columns
When a delay holds up the structure, the programme has to show whether it holds up completion too.

Keep it short. One or two pages of programme excerpt that the superintendent can follow is worth more than a full schedule export attached without explanation.

Why do capable builders still miss the notice window?

It is rarely a lack of knowledge. Your PM and CM know a notice has to go out. The window is missed because of how the job is run in the busy weeks.

  • The team waits until the full extent of the delay is known, and the notice period runs out while they wait.
  • The programme has not been updated for weeks, so nobody can show quickly whether the delay is critical.
  • Nobody owns the clock. The site team assumes the PM sent it, and the PM assumes the contract administrator did.
  • The notice is a generic reservation of rights that names no cause, no date and no effect on completion.
  • It goes by email to the wrong person, when the contract specifies a different recipient or method.
Timeline showing a delay event, a notice within the contract window, updated notices while the delay continues and the extension of time claim
Notify inside the window with what you know, then update the notice as the delay develops.

Each of these is a process gap rather than a skills gap, which makes it fixable before the next delay arrives.

How do you set up a notice routine that holds up?

The builders who rarely lose time on notices treat them as a routine, not an emergency. A few habits, agreed with your PM and site team at the start of the job, do most of the work.

  • Summarise the notice clauses in one page: periods, time bars, recipients and method.
  • Keep a notice register with the event, date, notice sent, programme reference and follow-up due.
  • Check the programme against new events every week, not just at the monthly update.
  • Use a notice template that prompts for cause, start date, work affected and likely effect.
  • Send updated notices while a delay continues, as many contracts require, until it ends.
Worker in a face shield and orange high-visibility harness using power tools at a timber workbench on site
Daily records of what was worked on, and what was not, are what confirm the dates in a notice.

The move from tender programme to contract programme is the right moment to set this up, together with the Basis of Schedule, because it fixes the baseline every later notice and claim is measured against. When a delay does turn into a claim, see extension of time claims and delay analysis methods.

 

FAQs

Do you need to know the full delay before sending a notice?

No. Most contracts expect notice when you become aware of the delay, not when you know its full extent. Notify with your current view, label the impact as preliminary and update it as the delay develops.

What happens if a delay notice is late?

It depends on your contract. Some standard forms include time bars that remove entitlement to more time if notice is not given within the set period, while others allow late claims in limited cases. Check the clause early and get legal advice if a notice has been missed.

Is an email a valid delay notice?

Only if the contract allows notices by email to that recipient. Many contracts specify the person, address and method for notices, so confirm this at the start of the job and keep proof of delivery.

Should a builder outsource delay notice programme support?

If your PM and CM are running a busy job and the programme has not been kept current, an experienced planner can status the programme, mark up the affected path and estimate the likely impact within the notice window. Your team still owns the notice; the planner supplies the programme evidence behind it.

Who offers programme support for delay notices and EOT claims in Australia?

FeelDX is an Australian project controls specialist firm with a construction background that supports builders with programme status updates, delay notice evidence, forensic programme analysis and EOT support, along with construction programmes, Basis of Schedule and 3D and 4D visualisation.

How does FeelDX support your delay notices?

FeelDX combines planning and visualisation so you can show how the job is being built, how long it will take and what it looks like, and reduce risk before a delay turns into a dispute. For delay notices, that means keeping the programme current through regular status updates, and when an event hits, turning it into evidence quickly: the affected activities, the path to completion, the float position and a preliminary impact you can send inside the notice window. See our project controls services and planning and visualisation technology.

  • Planning Lead. Once you give the go-ahead, a Planning Lead is assigned and introduced, so you know who you are working with.
  • Kick-off. A short meeting with your PM or CM on the contract notice clauses, current programme, live delay events and the records available.
  • High-level WBS. The first hold point: you confirm the programme structure and update cycle before the detail is built.
  • First draft with review time. The programme excerpt and preliminary impact arrive with enough time for your team to review them before the notice is due.