Construction programme updates should run fortnightly while the critical path is moving quickly, trades are stacked in the same zones or recovery is underway, and monthly on steadier, long-duration works with healthy float. Whatever the cycle, each update records actual progress at a data date, checks the logic and re-forecasts completion.
Most builders agree the programme should be updated. The real problem is that the update becomes a monthly reporting task, prepared the night before the client meeting, and nobody uses it to make decisions. This article is about choosing a cycle that matches the risk on your job and making each update worth the time it takes.
How often should a construction programme be updated?
Check the contract first, since many set a minimum frequency and a format. Above that minimum, the right cycle is the one that shows you a problem while you can still do something about it. If a slip on the critical path would cost you more in two extra weeks of not knowing than the update costs to run, update fortnightly.
Why do capable builders still update too late?
The programme was built well for the tender, then handed to a site team who are flat out running the job. Updates are done as a percentage complete on each bar, without revisiting logic or remaining durations. The end date stays green on paper until the month it suddenly does not.

When does fortnightly make sense?
- The structure or a key interface is on the critical path and moving week by week.
- Several trades are working in the same zones and sequence matters.
- The job is in recovery or acceleration, and you need to know whether it is holding.
- The client, lender or superintendent is tracking specific milestones closely.
Monthly suits long-duration works with few interfaces, a stable sequence and float that has not been touched. Many jobs move between the two: fortnightly through structure and the busiest fitout period, monthly either side.
What should every programme update include?
- A clear data date, with actual starts and finishes recorded against it.
- Remaining durations reassessed by the people doing the work, not just percent complete.
- A logic check: anything being built out of sequence is reflected in the programme.
- Re-forecast completion and key milestones, with the critical path and float compared with the last update.
- A short narrative: what moved, why, and what action is being taken.

If your commercial team runs a cashflow forecast off the programme, align the update with the progress claim cycle so both tell the same story.

Who should run the update?
The site team owns the progress information. Someone with planning skills needs to own the programme: entering actuals, checking logic and explaining what the forecast means. On many Tier 2 and Tier 3 jobs that is a PM or CM doing it on top of everything else. That works when the job is simple and the PM has the time. When it is not, a planner working alongside the PM keeps the update consistent without pulling the site team away from the job.
If your tender programme was never converted into a working contract programme, start there: our guide on tender vs contract programmes explains what changes after award.
FAQs
Is a monthly programme update enough?
It is enough on steady works with healthy float. On jobs where the critical path is moving or trades are stacked, a month is long enough to lose options you would have had two weeks earlier.
What is a data date in a programme update?
It is the cut-off point for progress. Everything before it is recorded as actual; everything after it is forecast. Without a clear data date, updates cannot be compared.
Should a builder outsource programme updates?
Outsourcing makes sense when your PMs are stretched or the contract requires a level of reporting your team cannot keep up with. A planner who updates the programme with your PM or CM keeps it accurate while your team stays on site.
Who offers construction programme updates in Australia?
FeelDX is an Australian project controls specialist firm that provides fortnightly or monthly programme updates, recovery programmes, cashflow forecasts and Microsoft Project training for builders, project management firms, developers and councils.
How does FeelDX run programme updates?
FeelDX brings planning and visualisation together so everyone on the job can see how it is being built, how long it will take and where the risk is. For ongoing updates we assign a Planning Lead, hold a kick-off with your PM or CM to agree the cycle, data date and reporting format, confirm the high-level structure of the programme, then deliver each update with enough time for your team to review it before it goes to the client. Where your team wants to run updates themselves, our project controls team also provides Microsoft Project training focused on using the programme as a risk tool.
Send us your current programme and your claim dates, and we will come back with a recommended update cycle and what the first update would involve.
Talk to FeelDX
📞 1800 FEELDX (1800 333 539) | 🌐 www.feeldx.com