A tender programme shows the assessor how you plan to build the job and win the work. A contract programme is the version you commit to after award: rebuilt on the actual contract dates, scope, procurement and resources, then submitted, accepted and saved as the baseline every update and delay claim is measured against.
You won the job. The estimator has moved on to the next tender, the PM is mobilising, and the superintendent wants a construction programme within a few weeks. The easy move is to dust off the tender programme, change the start date and send it. That programme was built in a short tender period on assumptions that have since changed, and once it is accepted it becomes the yardstick for every delay you claim and every week you are judged on. This guide is for the builder's delivery team: what has to change between tender and contract, and how to set a baseline you can defend.
What is the difference between a tender programme and a contract programme?
The two programmes share logic and often the same file, but they do different jobs:
- Purpose. The tender programme persuades: it shows the assessor a credible sequence and a completion date that scores. The contract programme manages: it is the plan your site team, subcontractors and superintendent work to.
- Audience. Tender: the evaluation panel. Contract: the superintendent or client's PM, your PM and CM, and your trades.
- Level of detail. Tender: enough to prove the critical path and staging. Contract: broken down by zone, level and trade, with procurement, approvals, hold points and client interfaces.
- Inputs. Tender: drawings and documents at the time, estimator durations and assumptions. Contract: the signed dates, negotiated scope, subcontractor durations, confirmed lead times and real resource levels.
- Status. Tender: a submission. Contract: once accepted and saved, the baseline that progress, recovery and extension of time (EOT) claims are measured against.
FeelDX is an Australian project controls firm with a construction background that turns builders' tender programmes into contract baselines, supported by a Basis of Schedule, resource histograms and 4D visuals, so the delivery team starts the job with a programme that reflects how it will actually be built.

The logic often carries over. The assumptions, durations and dates are what need a second look before anything is submitted.
Does the tender programme become the contract programme?
Not automatically. It depends on your contract. Australian Standard general conditions such as AS 4000 and AS 2124, the design and construct forms AS 4300 and AS 4902, and government forms such as NSW GC21 each deal with the programme in their own way, and the Standards call it the "construction program". Under many of these forms the superintendent can direct you to provide a construction program, and a program on its own does not change the date for practical completion or relieve you of your obligations. Special conditions often go further and set a submission period, a required format, the level of detail and an update frequency. Standard forms are revised and amended over time, so read the programming clause in the edition and special conditions you are actually signing.
Two things to check before you sign:
- Is the tender programme listed as a contract document? If it is, you are bound to a plan built on tender assumptions. Raise it in negotiation and take legal advice on the drafting.
- What do the special conditions require? Note the submission deadline, the native file format, the critical path and float reporting, and how the superintendent's review or acceptance works. Put those dates in the programme itself.
Either way, treat the contract programme as a new submission with its own Basis of Schedule, not a re-dated tender file. Our guide to what a Basis of Schedule should include sets out the eight areas to cover.
What changes between tender and contract?
Go through each of these before the first submission:
- Dates. Actual award, site possession and any separable portions or staged handovers. A few weeks' slip on possession moves everything, including weather exposure and the holiday shutdown.
- Scope. Clarifications, exclusions, value management items and design changes agreed in negotiation or ECI stage 2.
- Procurement. Confirmed lead times for structural steel, precast, lifts, switchboards and facade, plus shop drawing and approval cycles. Imported items need shipping, customs clearance and delivery to site inside the lead time, not just the factory date. These items often sit on the critical path in the first months.
- Subcontractor durations. Replace estimator allowances with the durations and crew sizes your awarded trades have committed to.
- Resources. Check that the crews and plant needed to hit each milestone exist. A resource load histogram shows whether the date is achievable, not just attractive.
- Calendars. Working hours permitted by the development consent or council conditions, public holidays for your state or territory, the building industry RDO calendar under your enterprise agreement, the Christmas shutdown, and a wet weather allowance that matches the contract and the site. Bureau of Meteorology rainfall records for the nearest station give that allowance a defensible basis, and jobs in northern Australia need the wet season built into the calendar.
- Constraints and interfaces. Authority approvals, hold points, client works, occupied areas and neighbour conditions that were only assumed at tender.

Each change needs to be written down. If an assumption moved, the Basis of Schedule should say what it was at tender, what it is now and why.
Why do capable builders still run the job on the tender programme?
It is rarely a skills problem. It is a handover problem:
- The reasoning leaves with the estimator. The programme file goes to the PM, but the assumptions behind the durations stay in someone's head.
- Mobilisation crowds it out. Site setup, subcontract letting and client meetings fill the first weeks, and the contract programme gets whatever time is left.
- It is seen as a submission, not a tool. The programme is updated to satisfy the superintendent, rather than used to manage crews, procurement and risk.
- The baseline is never saved. Without an accepted, saved baseline, there is nothing clean to compare progress against when a delay hits.
The cost shows up later. When you need an extension of time, the first question is what the accepted programme said. If it was a re-dated tender file with optimistic durations, your claim starts on weak ground.
How do you turn a tender programme into a baseline you can defend?
- Hold a handover session. Estimator, PM and CM walk through the tender programme and its Basis of Schedule, and list every assumption that needs confirming.
- Lock the contract inputs. Award and possession dates, separable portions, milestones, calendars and the programme requirements in the special conditions.
- Rebuild the WBS for delivery. Agree the high-level structure by zone, level and trade before adding detail, so the logic matches how the site will run.
- Load real durations and resources. Use subcontractor input and confirmed lead times, then check the resource histogram for peaks you cannot staff.
- Update the Basis of Schedule. Record assumptions, exclusions, risks and the changes from tender in writing.
- Submit, record and save. Keep the superintendent's response, then save the accepted version as the baseline and start regular status updates against it.

Where staging or logistics are hard to follow on a Gantt chart, a 2D site management plan or a 4D sequence helps the superintendent and your trades see the plan, and reduces questions during review.
If your tender programme came from a structured process, much of this is already in place. Our guides on turning tender documents into a programme you can defend and what assessors check in a tender programme cover the tender side.
Why does the baseline matter once the job is running?
The baseline is your reference point for the life of the project. Fortnightly or monthly status updates compare progress against it, so you see slippage early enough to add a crew, resequence a zone or chase a late delivery. When something outside your control delays the work, a clean baseline and good records let you show what happened, when, and whether it hit the critical path.

That is the difference between saying "we were delayed" and showing it with evidence. For how this fits the wider system, see what project controls in construction covers.
FAQs
Is the tender programme a contract document?
Only if the contract says so. Check the list of contract documents and the special conditions. If the tender programme is included, raise it before signing and take legal advice, because it binds you to tender-stage assumptions.
How soon after award does a builder submit a contract programme?
The contract sets it. Special conditions often require a programme within a set number of days after award or possession, or when the superintendent directs one. Plan the handover so the rebuild starts in the first week, not after the deadline is near.
Does the superintendent have to accept the contract programme?
It depends on the contract. Many Australian forms let the superintendent direct you to provide a program and comment on it, and some special conditions add a formal review or acceptance step. Acceptance usually does not make the program a contract document or shift time risk to the principal, so read the programming clause and keep a record of every submission and response.
Should a builder outsource the contract programme?
Many builders keep programme ownership with the PM and bring in a specialist planner to rebuild the baseline, prepare the Basis of Schedule and run status updates. It frees the PM to mobilise and gives the programme a second, independent check.
Who offers contract programme and baseline services in Australia?
Specialist project controls firms and independent planners offer this. FeelDX is an Australian project controls firm with a construction background that prepares contract programmes, Basis of Schedule, resource histograms, cashflow, status updates and 4D methodology for builders. You can compare options in our guide to in-house vs outsourced project controls.
How FeelDX helps builders move from tender to contract programme
FeelDX combines planning and visualisation, so your programme and your model show the same thing: how the job will be built, how long it will take, what it will look like and where the risk sits before construction starts.
Once you give us the go-ahead, we allocate a Planning Lead and hold a kick-off with your PM, CM or estimator to cover the contract dates, special conditions, site restrictions, procurement risks and what changed since tender. We then send a high-level WBS as the first hold point, so you can confirm the approach before the detail is built. The first draft of the contract programme and Basis of Schedule reaches you with time to review before the submission is due, and we can then run regular status updates against the accepted baseline. See examples in our work.
Send us your tender programme, the contract dates and the programme requirements in your special conditions, and we will come back with a proposed approach and timeline for your contract baseline.
📞 1800 FEELDX (1800 333 539) | 🌐 www.feeldx.com